Would it be a good idea to cut out the holes for the inspection ports before wiring things together? Thanks, Paul
2 replies:
RE: Skerry inspection hatch
I did it after the boat was put together and it was difficult to do! I eventually worked with the boat upside down with a little keyhole saw and it fought me all the way. CUT IT BEFORE ASSEMBLY! Christine














RE: Skerry inspection hatch
» Submitted by Bob Santore - Sun, July 13 » 8:18 AM
I did it that way, and didn't have any problems later. I'm sure it is much easier to do it before the frame panels are wired in.