Re: glue globs in cockpit
Posted by Jim E on Sep 12, 2006
Wow, 6 days is just 3 weekends to those of us that think that way. Some gloppy bits are excusable! I'm trying to imagine how the schedule would go for such a quick build, assumimg a Cheaspeake kit:
1: Scarfs (using fast hardener), sheer clamps scarfed and glued to side panels in one operation.
2: Wiring, interior filleting, glassing.
3. De-wiring, exterior glass.
4: Shape sheer clamps, fit Deck.
5: Glass on deck
6: Coaming, hatches
Which leaves no time for sanding or finshing. Has to be something like that.