We have almost finished three boats we started on July 7th.

Boat number one, a 17 LT and mine, we finished in 68 days. The deadline was set by a scheduled paddle trip in the San Juans. It was done completely, but that took working most of the 68 days.

The other two need varnishing and then fitting out the cockpits and deck fittings. I'm doing one of those, my wife's.

We actually took about a week after getting the kits before we actually mixed our first epoxy.